Consistent product quality, timely delivery and logistical control are crucial to a continuous pour project. With a Reimer Mixer, as long as the materials bins are charged, the mixer can continuously mix and deliver consistent, fresh concrete without the need for transit between the pour site and a batch plant.

CASE STUDY:

192-HOUR POUR: NO REJECTED LOADS

PTC Construction is one of very few companies in North America that construct grain terminals using slip forms. The logistics schedule for this type of work is massive. Managing concrete delivery and training crews, installing rebar, placing bulkheads and operating 7 X 24 until the pour is finished. Once a slip form pour starts it cannot stop. All elements of the supply chain need to keep working. Everything from mechanical or electrical failures, mixer travel times to bad weather needs to be planned for. One hiccup and the whole job becomes more complex.

Justin Patterson, project engineer/manager for PTC Construction remarks “the Reimers have been a real success story for this project; we’ve had continuous control over the mix and have never had a rejected load.”

The concrete supplier for this project was LPR Concrete, based in East/Central Alberta. With 50 years of combined experience with mobile volumetric mixers, the ownership group targets projects that present unique concrete supply challenges and offers contractors solutions and services that this mixing system can provide. Not only does LPR provide volumetric mixing solutions for contractors, it also proves to be a more profitable part of their business. When asked to bid on the concrete delivery for a new grain terminal complex using a slip form to construct the grain terminal and traditional forming for bases and pads, LPR knew they could provide a unique solution for PTC Construction. Rather than putting a portable batch plant on site where it would sit idle in between pours, LPR pitched the benefits of using mobile mixers.

COMPLEX PROJECT

Concrete pours for the entire project were scheduled intermittently over a number of months, culminating in a continuous, 8-day slip form pour for the terminal itself. When there was no pour scheduled, the Reimers could be driven off to be used at other locations. This left only a loader, cement silo and raw materials at the site. When concrete was scheduled, 3 or 4 mixers could be driven to the site, charged and would produce up to 600m3 a day. Once the slip form pour started, 2 Reimers were continually charged for 192 hours, with a third Reimer standing ready as back-up.

LPR could show that with very few assets on the site and a unique ability to deal with changes in temperature that volumetric mixers were the best way to go. During the 8-day slip form pour which occurred at the end of October, temperatures ranged from -10⁰C to +6⁰C.

Hot water was used and steamed sand was available to ensure that the concrete maintained a constant temperature. There is huge advantage to the contractor in not having to plan for whatever could go wrong at the batch plant, or dealing with delays in transit mixers getting to the site. “Each Reimer is virtually its own batch plant, so we had triple redundancy on-site which is much easier to manage than a ready-mix plant 60 kilometers away” states Larry Hooper one of the partners in LPR Concrete.

REDUCING RISK

Because of the nature of slip form construction, long supply lines can become a logistical nightmare. At one point in the pour a pump clogged. This shut down the pour for approximately 3 hours. “If a traditional ready-mix operation had been employed, there would have been a lot of rejected loads and wasted concrete with transit mixers having to wait for several hours. The nearest Ready-Mix operation is over 45 minutes away, which would mean we would be tying up a lot of resources and assets in order to complete this pour. Not to mention all the back-up and redundancy that would be required at the batch plant. Once we start pouring we must continue, so spare parts, back-up generators would all have to be on-site and capable of being deployed immediately if there was a problem. With the Reimers, we could simply stop production until the clog was fixed and then start right back up again” commented Patterson.

SAVING MONEY – LOWER COSTS

Delivery from a traditional batch plant would have at least 2 batchmen, one or two quality control people on-site. Additionally, it would have tied up 6 trucks and drivers (2 mixers on-site at all times; 1.5 hours travel time to and from the batch plant to the site) for over a week. Instead with the Reimers, three men worked the night shift and four men worked the day shift. The 32MPA mix design was engineer-specified, each load was slump and air tested.

During the pour, cylinders were taken every 50 meters. Because the concrete is mixed fresh on site, changes to the mix design to comply with the specification could easily be done at that particular moment – something that couldn’t possibly be done using a traditional batch plant. Hooper elaborates “If we had troubles with the concrete we’d have to phone over to the batch plant for remediation, then depending on the timing, there could have been 1 or 2 trucks on-site to be discharged, another truck on its way that could mean a lot of rejected concrete before the batchman could remedy the mix.”

 

“The Reimers have been a real success story for this project; over 8 days we’ve had continuous control over the mix and have never had a rejected load.”

Reimer Case Study Continuous Pour

 

 

Drum Mixers / Static Batch Plant

Mobile Volumetric Mixers

Manpower 2 Batch Men 192 4 Day Shift (Operators, QC, Loaders) 384
2 QC 192 3 Night Shift (Operators, QC, Loaders) 288
12 Drivers 1152
16 Men 1536 Hours 7 Men 672 Hours

 

Assets
6 Transit Mixers 2 Reimer Mixers (double redundancy)
1 Batch Plant (w/hot water system) 1 Wheel Loader
1 Wheel Loader 1-50 Tonne Cement Silos
1 Standby Generator 10,000 Gallon Water Tank
1 Alternative Batch Plant (redundancy requirement) 3,000 Gallon Heated Water Tank